Progress continues on the Ballard 1000 South Roosevelt 800 South road project. The cast-in-place concrete box culvert is now fully finished and crews are continuing to backfill around the completed box culvert. Storm drain installation is also underway on the east side of 1000 South. Roosevelt City has expressed thanks for the continued patience as crews work to improve roadway connections in the Roosevelt community.
Photo: Roosevelt City FB